|
Northwest
Corner
Construction
Updates
Harvard Law School
Northwest Corner
Construction Update
July 4th, through July 11th, 2008
No work will be performed on Friday, July 4th in
observance of the holiday.
Saturday 7/5/08
- No work will be performed this Saturday 7/5/08.
Site Activities
–
- Miscellaneous chipping will take place over the next
few weeks with a small excavator.
- Backfilling activities will continue in the tunnel
area.
- Backfilling and demolition activities on the support
of excavation will take place on the south wall this week.
- Material will continue to be hauled offsite this week.
- Resizing of the guide wall debris will continue.
- Forming and pouring activities will take place for the
cap beam this week along the south and the southeast end of the site.
- The stone will be removed from the mock-up this week.
Disposal pick-ups will take place through the Lewis Lot.
- Work on the new water line between Harkness and Pound Hall
will continue. A water shutdown is scheduled for Friday 7/11/08 in Harkness.
This work will take place off hours.
- Miscellaneous demolition and exploratory work will
take place in Harkness this week. No building systems will be affected
unless it has been approved and coordinated.
- Coring activities will take place from the second
floor of Harkness. This work will be completed between the hours of 4am-7am
Monday through Wednesday.
- Steel erection and the installation of metal decking
will continue this week. Welding equipment will be utilized to complete this
work.
- Standpipe upgrades will continue in Pound Hall this
week. This work will take place during the 3rd shift to avoid disrupting the
building occupants.
Northwest Yard Utility Upgrades
Construction Update
July 4th, through July 11th, 2008
A 72-hour chilled water shutdown has been scheduled for
Thursday, July 3rd at 6pm through Sunday, July 6th, 2008. This shutdown will
affect the air-conditioning units in Pound, Harkness and Hauser. Austin Hall
will be available to students, faculty, and staff as an alternate study/work
area during this shutdown.
Saturday 7/5/08 & Sunday 7/6/08
- Chilled water connections will continue throughout the
weekend. Saw-cutting activities will be performed during this work.
Site Activities
–
- Work on the electric manhole expansion will continue
this week.
- Steam and condensate pipe welding will continue
throughout the week.
- The covered walkway between Harkness and Child will be
closed to pedestrian traffic. Pedestrians will be rerouted near Jarvis
Field. The handicapped access between Harkness and Child will be maintained.
- Pipe installation in the basement of Childs will
continue this week.
If you have any questions or concerns
please contact the
Mitigation Hotline at 617-496-0857 |