|
Memorial
Housing
Project
Updates
10 Akron Street Housing Project
Construction Update
July 4th through
July 11th, 2008
Friday 7/4/08
Saturday 7/5/08
-
Bond Brothers will be on site
this Saturday completing both interior punch list items, including the
garage, and exterior landscaping.
-
Work will begin at 9am per the
City of Cambridge Noise Ordinance.
Site Activities
·
Landscaping
activities will continue along the Memorial Drive side of the site. This work
will include the planting of trees, shrubs and the installation of sod.
·
The Memorial Drive sidewalk reconstruction will continue. Pedestrians will
be detoured down Hingham St. Police details will be
present to ensure safety.
·
The architectural site fence will be delivered and installed next
week.
·
The site trailer is expected to be removed from the site the week
of 7/14/08.
·
The Memorial Drive project will utilize Watts Security to patrol
the site on a nightly basis.
Interior Work
· Interior punch list items will continue to be completed this week.
· Work
on the Director's Suite in the East Building will continue.
Garage Work
· Miscellaneous
punch list items will continue to be completed.
· Final
line striping will take place this week.
If you have any questions or concerns please
contact the
Mitigation Hotline at 617-496-0857
|